[ACI] Extended maintenance UP eCommerce Payments VM Hypervisor Patching - Limerick
Scheduled Maintenance Report for Cybersource Card Present
Completed
The scheduled maintenance has been completed.
Posted Apr 03, 2020 - 07:01 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 02, 2020 - 23:30 CEST
Scheduled
ACI will be deploying patches to the host devices for our virtual machine hypervisor software in our Limerick data center. These host devices are used by the applications shown below. Please note that our SFTP (file transfer) platform is also in scope of this change.

This scheduled maintenance has been extended by one day.
Posted Apr 02, 2020 - 19:18 CEST
This scheduled maintenance affected: Connectors (American Express, Concardis).